How far ahead do I need to plan my project?

My general suggestions are to give it more time than you think you are going to need. During the warmer months it can take 1 to 2 weeks just to set up appointments with contractors. It always takes longer than you think. The following are some rough times for planning your project.

Roofing, Siding, Windows

4 to 6 weeks

Exterior work can get booked up fast in the summer and fall. Winter might be a good time to get on someone's schedule.

Bath Remodeling

6 to 8 weeks

Allow time for planning and tweaking of ideas. You will need a permit and drawings. Permits can take up to a month to acquire.

Kitchen Remodeling

8 to 12 weeks

There is a lot of planning that goes into a kitchen. It will take time to work out all the small details that go into a well planned kitchen. You will need drawings and permits. It can take 6 to 8 weeks to order most cabinets.

Room Additions

3 to 6 months

You will need architectural drawings. This can take from 1 month to 3 months to get final working drawings. Once you have the drawings you will have to get prices from a builder. You will also need permits which can take 2 to 4 weeks.

New Homes

3 to 9 months

Custom homes will require all the items in room additions. Planning can take a little longer.

Repairs

2 to 4 weeks

If possible give this plenty of time. Most contractors are glad to do this work.